South Harbor Construction Update – August 15, 2024

Aug 15, 2024Public Notices, South Harbor Rebuild Press Releases & Public Notices

South Harbor Construction Update
August 15, 2024

– Waterfront parking along Nicholoff Way is now open. The new parking layout is diagonal, please park accordingly.

– A walking path and guardrail are open along the parking area.

– ADA-compliant/handicapped parking spots are located on the concrete pads at the western gangway, Fisherman’s Memorial, and Drive Down Float eastern access.

– Temporary floats will be removed soon, and the North Fill Launch Ramp will be operational.

– All slips in the South Harbor are ready for use with water services available, but electrical services are still being finalized.

– The Drive Down Float is still in construction

The City of Cordova appreciates everyone’s patience as they work towards completing the project and making the harbor fully operational.

For questions regarding berths, please reach out to the Harbormaster’s Office at (907) 424-6400.