Feb 12, 2024 | Public Notices, South Harbor Rebuild Press Releases & Public Notices
Construction crews from Turnagain Marine Inc. and GMC Contracting Inc. will continue to construct the new South Harbor now that demolition has neared its end. Roadside construction along Nicholoff Way requires a partial closure of the roadway just west of the AC...
Jan 19, 2024 | Public Notices, South Harbor Rebuild Press Releases & Public Notices
South Harbor Construction Progress Update: Demolition Nearly Complete – Float Installation to Commence Saturday, January 20th As demolition of the South Harbor reaches its final stages, construction crews from Turnagain Marine Inc. and GMC Contracting Inc....
Dec 27, 2023 | Public Notices, South Harbor Rebuild Press Releases & Public Notices
Demolition on the South Harbor is nearing completion. Crews will return the first week of January to finish demolition and disposal and begin assembling the new harbor structures.
Dec 1, 2023 | Public Notices, South Harbor Rebuild Press Releases & Public Notices
Harbor Construction Scheduled to Begin on December 6, 2023. Construction crews from Turnagain Marine Inc. are schedule to arrive in Cordova December 5, 2023. Barges and heavy equipment will be operating in and around the South Harbor for the next six months. The City...
Sep 28, 2023 | Public Notices, South Harbor Rebuild Press Releases & Public Notices, Uncategorized
In preparation for South Harbor construction the City of Cordova is asking that all vehicles parked in the lot on the southwestern side of the South Harbor and at the end of Nicholoff Way be removed no later than October 9, 2023. This area is outlined in red in the...
Sep 19, 2023 | Public Notices, South Harbor Rebuild Press Releases & Public Notices
The Cordova South Harbor Project will begin demolition on October 9th. Turnagain Marine Inc. of Anchorage is the primary contractor leading the project. We have had many inquiries about work opportunities. Currently, there may be a need for trained and certified...